Decisions Logs for ALL

626 Decisions of the Police and Crime Commissioner for Gwent from All Years

PCCG-2012-010  Finance Performance Report to 31st October 2012

The Police and Crime Commissioner for Gwent has monitored the financial position of the Force and is satisfied with progress.

PCCG-2012-010

Date Of Report: 13th December 2012

As part of the Commissoners monitoring duties under section 17 of the Policing Protocol Order 2011, the financial position of the Force has been monitored.

A £4million deficit had been projected for 2016/17; further discussions would be needed in order to identify how this saving was to be made. We requested more detailed explanations were provided on the Medium Term Revenue Projections 2012/13 to 2016/17 Assumptions appendix and that further detail on the reing-fenced reserves was also provided.

Show More
PCCG-2012-011  Updated 2013/14 Budget Briefing Report

The Police and Crime Commissioner for Gwent has been briefed on the budget process for 2013/14 and is satisfied with progress.

PCCG-2012-011

Date Of Report: 13th December 2012

A £4million deficit had been projected for 2016/17; further discussions would be needed in order to identofy how this saving was to be made. We requested more detailed explanations were provided on the Medium Term Revenue Projections 2012/13 to 2016/17 Assumptions appendix and that further detail on the reing-fenced reserves was also provided.

Further reports were to be provided to the Joint Audit Committee and to the Police and Crime Panel in January 2013.

Show More
PCCG-2012-012  Provision of an Internal Audit Service

The Police and Crime Commissioner for Gwent has approved the request to extend the current contract for the provision of an internal audit service.

PCCG-2012-012

Date Of Report: 13th December 2012

The Commissioner has been asked to approve the request to extend the current contract for the provision of an internal audit service by 24 months under the Police and Crime Commissioner for Gwent, Governance Part 5 Standing Orders Relating to Contracts, paragraph 125.

Show More
PCCG-2012-013  Provision of Driver Education Offender Rehabilitation Scheme(s) Speed Awareness

The Police and Crime Commissioner for Gwent has agreed to extend the current contract with TTC 2000 for the provision of driver education offender rehabilitation scheme(s) for 12 months.

PCCG-2012-013

Date Of Report: 13th December 2012

The Commissioner has been asked to approve the request to extend the current contract with TTC 2000 for the provision of driver education offender rehabilitation scheme(s) for 12 months under the Police and Crime Commissioner for Gwent, Governance Part 5 Standing Orders Relating to Contracts, paragraph 125.

Show More
PCCG-2012-014  Complaints Protocol and Procedure for Dip Sampling of Complaints

The Police and Crime Commissioner for Gwent has approved the protocol on complaints and the procedure for dip sampling.

PCCG-2012-014

Date Of Report: 13th December 2012

The Commissioner has been asked to approve the protocol on complaints and the procedure for dip sampling. The protocol and the dip sampling procedure are required under section 17 of the Policing Protocol Order 2011, to ensure guidelines are established for the monitoring of complaints.

Show More
PCCG-2012-015  Commissioning

The Police and Crime Commissioner for Gwent has agreed to develop a commissioning framework. The Commissioner also agreed to continue funding the community safety partnerships, the drug intervention programme and the youth offending teams in the sums prov

PCCG-2012-015

Date Of Report: 13th December 2012

The Commissioner has been asked to agree that a commissioning framework be developed over the next 12 months to oversee the provision of grants as set out under section 9 of the Police Reform and Social Responsibility Act.

Show More
PCCG-2012-016  Strategic Risk Management Proposal

The Police and Crime Commissioner for Gwent has agreed to maintain the existing joint approach to strategic risk management and has confirmed the Chief Executive will represent the Office of the Police and Crime Commissioner on the Business Tasking and Co

PCCG-2012-016

Date Of Report: 13th December 2012

There is currently a two-tiered approach to managing risk within the organisation. The strategic level which involved management of high level, corporate risks that will impact the Force as a whole and the achievement if Force objectives and the organisational level, whereby risks are managed on a local and departmental level.

The Commissioner has therefore been asked to continue with the current approach to monitoring strategic risk and to establish a new risk register for the Office of the Police and Crime Commissioner.

Show More
PCCG-2012-017  Membership of Joint Audit Committee

The Police and Crime Commissioner for Gwent and the Chief Constable for Gwent confirmed the three provisional appointments to the Joint Audit Committee and agreed to progress with the appointment of two additional members.

PCCG-2012-017

Date Of Report: 13th December 2012

The Financial Management Code of Practice for the Police Service of England and Wales requires that a Police and Crime Commissioner and Chief Constable establishes an Independent Audit Committee and recommends this should be a combined body.

Following an open recruiting process three of the five independent members of the Joint Audit Committee were appointed, subject to confirmation foloowing the election of the Police and Crime Commissioner, from the 30th September 2012 for a period of five years.

Show More
PCCG-2012-018  Provision of High Performance Vehicles

The Police and Crime Commissioner for Gwent has approved the contract for the provision of high performance vehicles to BMW for 2 years with an option to extend for a further 1 year.

PCCG-2012-018

Date Of Report: 13th December 2012

The Commissioner has been asked to approve the request to award a contract for the provision of high performance vehicles to BMW for 2 years with an option to extend for a further 1 year under the Police and Crime Commissioner for Gwent, Governance Part 5 Standing Orders Relating to Contracts, paragraph 88, most economically advantageous tender.

Show More
PCCG-2012-019  Performance Report against the Local Policing Plan 2012/13

The Police and Crime Commissioner for Gwent has monitored the overall performance of the Force and is satisfied with progress.

PCCG-2012-019

Date Of Report: 13th December 2012

As part of the Commissoners monitoring duties under section 17 of the Policing Protocol Order 2011, the overall performance of the Force has been monitored.